Abstract
This paper presents the results of geomechanical studies of the siltstone massif carried out in the right-bank experimental adit at the site of the Pskemskaya HPP dam. Primary shear experiments were carried out at the following 6 normal pressures on the stamp σ: 0.5 MPa; 1.0 MPa; 1.5 MPa; 2.0 MPa, 2.5 MPa and 3.0 MPa.
Article Details
How to Cite
Назаров Комил Игамбердиевич, Хидоятов Захиджан Даливаевич, & Хидоятов Абдуллох Захиджон ўғли. (2023). ENGINEERING AND GEOTECHNICAL SURVEYS AT THE SITE OF THE MAIN STRUCTURES OF THE PSKEM HYDROELECTRIC POWER STATION ON THE PSKEM RIVER. Spectrum Journal of Innovation, Reforms and Development, 14, 221–226. Retrieved from https://sjird.journalspark.org/index.php/sjird/article/view/631